Monday, August 20, 2012

Finishing Out The Master Bathroom

It's been a couple of years since work commenced in the Master Bathroom, and it still isn't finished. But, it's getting close. The progress note for today lists the remaining tasks that need to be accomplished, and additionally, I have to rewire and and a second vent into the bathroom, and re-insulate the ceiling. On hot Dallas summer days, the room heats up and makes the entire house warm. This is due to the removal of insulation during the shower remodel.  Pics are forthcoming and will be added to this post by the end of the day.

PICTURE NUMBER 1 - Bathroom Starting Point
PICTURE NUMBER 2 - Bathroom Starting Point
PICTURE NUMBER 3 - Post Demolition
PICTURE NUMBER 4 - Progress Point (Flooring)
PICTURE NUMBER 5 - Progress Point (Shower)
PICTURE NUMBER 2 - Progress Point (Shower)
PICTURE NUMBER 2 - Progress Point (Doorway)
PICTURE NUMBER 2 - Progress Point (Doorway)
REMAINING PICTURES - Finished Bathroom






Progress Notes - Sunday 8/19/2012







MASTER BATHROOM
  • Removed Old Pocket Door
  • Prepped Doorway for New Flooring
  • Installed and Removed Flooring
      UPCOMING PLANS
    • Paint New Pocket Door
    • Cut and Reinstall Flooring
    • Hang Shower Handle 
    • Fix Window Sill
    • Stain Flooring
    • Hang Door Frame 

Sunday, November 20, 2011

Fuchsia's Blue Kitchen (Before Pictures)

Full Kitchen / Nook  |  West View
Prep Kitchen / Nook  |  North View

 Prep Kitchen  |  West View
Prep Kitchen  |  North View

Kitchen Pantry  |  South View
Nook | East View


Kitchen  |  Den (West) View

Friday, November 18, 2011

Weekend Task List

ELECTRICAL
  • PRINT UP PANEL IDENTIFIERS
  • DRAW UP AND SAVE MASTER DIAGRAM OF OUTLETS
  • PULL WIRE TO LINE ONE
  • REPLACE LINE ONE OUTLETS
  • ADD NIGHT STAND OUTLETS TO LINE ONE
  • FIX ELECTRICAL MESS IN GARAGE
  • ADD OUTLETS AND SWITCHES TO KITCHEN
  • PUBLISH MASTER DIAGRAM TO FUCHSIA 715
PAINT AND PLASTER
  • FINISH KITCHEN CEILING REPAIR
  • TEXTURE KITCHEN CEILING
  • TEXTURE KITCHEN WALL
  • PRIME/PAINT KITCHEN
  • PAINT BRICK FIREPLACE
  • PAINT MASTER BATHROOM
  • CHALK BATHROOM WINDOW
CONSTRUCTION PROJECTS 
  • BUILD FAUX WALL IN BONUS ROOM
  • MOVE GAS LINE IN BONUS ROOM 
  • BUILD UPPER CABINETS
  • HANG UPPER CABINETS

Shopping Lists

PURCHASES TO BE MADE
  • IKEA - Small Hand Pulls
  • HOME DEPOT - Shower Rod
  • HOME DEPOT - Shower Fixture
  • HOME DEPOT - White Mortar
  • IKEA - Window Blinds
  • BED BATH AND BEYOND - Shower Curtain
  • HOME DEPOT - Hand Sander
  • HOME DEPOT - GFI Switches
  • HOME DEPOT - Cement Bolt's 
  • HOME DEPOT - Cement Blocks
  • IKEA - Cabinet End
  • HOME DEPOT - Insulation
RETURNS
  • HOME DEPOT - Shower extender
  • TIME WARNER - Second DVD Box
  • TIME WARNER - HBO

Monday, November 14, 2011

Progress Notes - Monday


KITCHEN
  • Covered Hardwood Floor
  • Taped and Mudded (for the umpteenth time)  

Sunday, November 13, 2011

Progress Notes - Sunday Activities

KITCHEN
  • Built Two Kitchen Cabinets
  • Built Nook For Fridge (Dead Space)